Due to work on the utility lines, several roads in Biemenhorst will be partially closedWork on utility lines: Five streets in Biemenhorst affected
Construction work in Biemenhorst // From the end of November until, it is expected, mid-April 2027
Due to work on the utility lines, several roads in Biemenhorst will be partially closed. Local residents will be informed in good time; no diversions will be put in place.
The renovation work will begin on 24 November 2026 and is expected to last until mid-April 2027. Several roads in Biemenhorst are affected; the work will take place in five consecutive phases. Â
On site
There will be several excavation pits within the carriageway. Road closures are planned for a maximum of five days; footbridges will be set up in the pavement area. Due to a pipe trench at the kerb, a remaining carriageway width of 3.5 metres will be maintained at house numbers 12 to 20 and 76 to 86. Access for residents will be guaranteed outside working hours.
At the playground
Due to a pipe trench in the carriageway, the road will be closed for a maximum of five days near the playground. Outside working hours, the trench will be covered with steel plates. The playground will be closed whilst the works are in progress.
In Esch
Along the entire length of the road, a residual carriageway width of at least 3.5 m will be maintained due to a pipe trench at the kerb. Access for residents will be guaranteed outside working hours.
In the Flur
Due to a pipe trench at the kerb, a minimum remaining carriageway width of 3.5 metres will be maintained along the entire length of the road. Access for residents will be guaranteed outside working hours.
On Dannenkamp
Excavation pits are being set up at house numbers 36 and 46, leaving a minimum remaining carriageway width of 3 metres in this area.